Projected time line: Estimated ship date: Dec 13, 2013
Project design and drawings began: April 29, 2013
Release to production: September 4, 2013
Mix/Homo tanks ordered: September 6, 2013 Projected completion: October 31, 2013
Catwalk on order, however on hold until final drawings have been completed. Pending
Main skid: See below
Hydraulic component ordered: 9/10/2013: Projected ship date: November 10, 2013
C Pumps with motors ordered: September 4, 2013 Projected ship date: September 26, 2013
Hose Reel with Teflon rollers ordered September 4, 2013 Projected ship date: October 21, 2013
Blower and hydraulic motor ordered: September 4, 2013 Projected ship date: September 17, 2013
Air actuated Keystone valve 222 lugs style, molded in design for harsh environment with stainless disks. Ordered: September 4, 2013 Projected ship date: October 15, 2013.
Olin combined skid: See Below. Waiting on design input.
Main skid: Production drawing released: September 11, 2013 Projected completion September 27, 2013 MainSkid.jpg
Final Drawing, Canadian specs:
Control Panel in review. Currently on revision #4. Rev # seems to be close to what Chris wants. Waiting on controls guy for drawings.
Murphy Power View: 101C order pending waiting on cord length requirement.
Waiting on agitators and support bearing from Morganic. Will follow up September 14, 2013.
|