Projected time line:  Estimated ship date: Dec 13, 2013
 
Project design and drawings began:  April 29, 2013
 
Release to production:  September 4, 2013
 
Mix/Homo tanks ordered:  September 6, 2013  Projected completion:  October 31, 2013
Catwalk on order, however on hold until final drawings have been completed.  Pending
Main skid:  See below
Hydraulic component ordered:  9/10/2013:  Projected ship date:  November 10, 2013
C Pumps with motors ordered:  September 4, 2013  Projected ship date: September 26, 2013
Hose Reel with Teflon rollers ordered September 4, 2013   Projected ship date: October 21, 2013
Blower and hydraulic motor ordered:  September 4, 2013   Projected ship date: September 17, 2013
Air actuated Keystone valve 222 lugs style, molded in design for harsh environment with stainless disks.  Ordered: September 4, 2013   Projected ship date: October 15, 2013.
 
Olin combined skid:  See Below.  Waiting on design input.
 
 
 
 
 
Main skid:  Production drawing released: September 11, 2013  Projected completion September 27, 2013    MainSkid.jpg
 
Final Drawing, Canadian specs:
  
Control Panel in review.  Currently on revision #4.  Rev # seems to be close to what Chris wants. Waiting on controls guy for drawings.
Murphy Power View:  101C order pending waiting on cord length requirement.
 
Waiting on agitators and support bearing from Morganic.  Will follow up September 14, 2013.
 
Final video: Should be available by Sept 16,2013.  http://youtu.be/JzetEj1hxjk